PERI plays a key role in the construction of GIOIA 22, a 120m tower in Milan
By Edit Team | March 16, 2020 5:07 am SHARE
GIOIA 22 is the first 120 m tower in Italy to meet the NZEB standard (nearly zero energy consumption building). A characteristic feature of the building is its folded shape which is of ecological significance in addition to being aesthetically pleasing.
Project specific solution for an exceptional design
The building consists of a main core with 26 floors and a secondary core with 13 floors. The special feature: from the second floor upwards, the tower starts to fold in on itself so that the slabs become wider with each passing floor. A project-specific combination of different systems was required to create the unusual shape of the building. Moreover, the construction work had to be completed as quickly and efficiently as possible in order to meet tight deadlines. For these reasons, the decision was made to combine the SKYDECK Slab Formwork with an additional RCS P System Solution to realise the slabs from the second floor upwards. Systematic erection sequences and lightweight system components made it possible to complete an entire floor in a week.
Characteristic features of the building are the 17 round columns of which seven columns are inclined. They were erected using SRS Circular Column Formwork. With their high-quality, architectural concrete surfaces, the columns are also aesthetically pleasing. The diameter of the columns vary between 1.0 m and 0.8 m, becoming smaller with the increasing height of the tower.
The client used approximately 1,000 m² of TRIO Panel Formwork to erect the wall space in both cores. The TRIO System was combined with the BR Shaft Platform and the RCS C Rail Climbing Formwork to form the staircases and lift shafts. A particular highlight was the use of the ACS P Self-Climbing System. It allowed the lifting of the 32 m long concrete distribution arm from floor to floor.
Customised climbing solution facilitates connection of both building cores
17 RCS P Climbing Protection Panel Systems with guided rails were used for the building section with consistent geometry. These systems were affixed to the structure at all times. In this way, the RCS P Climbing Protection Panel was anchored to the RCS Slab Shoe and Climbing Shoe on the floor slab which, in turn, were affixed with M24 Climbing Anchors. 15 non-guided, crane-climbed RCS P Climbing Protection Panels were used for the inclined section of the tower. In addition, a diagonally-climbed RCS Protection Wall Unit was used and moved without a crane using a mobile climbing hydraulics system.
The process of connecting the main core of the building to the secondary core was one of the key technical challenges of the project. To achieve this, the first RCS Climbing Unit was installed using vertical as well as laterally inclined climbing rails. The cantilevered section of the roof slab on the 25th floor, which, at 10 m, is twice as high as the other floors, was implemented with the aid of PERI UP Flex Shoring Towers. They were supported by RCS Climbing Rails and Steel Walers that were anchored to the slab.
Sophisticated safety concept
Safety at the jobsite was of paramount importance despite the need to achieve quick results: the RCS P Climbing Protection Panels were used for gap-free enclosure of the floors in the building shell. On the one hand, they served as guardrails, but also provided additional protection from the wind and prevented objects from falling off the building. In addition, over 4,000 linear metres of PROKIT were used as guardrails on building edges. This meant that the construction site team could work safely and efficiently at all times.
Efficient transportation of materials
Two RCS MP Material Platforms were used to move essential materials from one floor to another. The platforms were the ideal means of transportation on the jobsite due to their high load capacity and flexible mounting options. They made it possible to move packages with dimensions of up to 5.30 m x 2.30 m and weights of up to 3,000 kg.
Cookie Consent
We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.