B2B Purchase - Project Procurement Professionals

TCI
TCI
B2B Subscription
B2B Subscription
Home » Uncategorized » Finland’s Jumbo shopping centre extension: modelled with Tekla Structures

Finland’s Jumbo shopping centre extension: modelled with Tekla Structures

By | August 21, 2014 4:34 am SHARE

B2B Purchase
.

The use of BIM on a construction site was put to the biggest test to date in Finland in connection with the extension of a shopping mall in the capital region. The building project was a pilot in the utilisation of a 4D building information model produced with Tekla Structures software for planning and steering site operations. The benefits of 4D modelling truly came into their own when the project’s tight schedule was jeopardised by a several week delay.

The frame construction of the 72,000 sq.m., 400,000 cubic metre extension of the Jumbo shopping mall near the Finnish capital Helsinki began in March 2004. The completion of the extension was scheduled for late 2005 to get business premises up and running for the Christmas sales. The project management contracting was carried out by Lemcon Finland.

Project Director Juha Höyhtyä explained that a tight timetable meant that the design, purchasing, prefabrication and site activities ran very much in parallel. “The traditional method of completing the design project before starting anything else wouldn’t have been possible here. Instead, design work began on the sections that were to be handed over first, and purchases were divided into reasonably sized entities,” Höyhtyä described.

Due to its nature, the building project was selected as a pilot for the ‘Pro IT – Product Model Data in the Construction Process’ project by the Confederation of Finnish Construction Industries. The objectives of the Jumbo extension pilot included testing the combining of the frame’s concrete and steel structures into a single Tekla Structures model and testing the deployment of the model for scheduling site activity. In addition, experiences were gathered concerning the usability of programs, model-based data transfer, and data sharing between organisations.

One model for steel and concrete structures plus schedules
Jumbo’s design had advanced quite far when Pro IT’s piloting began. The steel structures were under planning with the Tekla Structures modelling software, and traditional 2D drawing had already been selected as the design method for concrete structures and shells. For the purposes of the pilot, the concrete structures’ geometries were also modelled with Tekla Structures. Site management was further improved by combining the steel and concrete frame and facade shell models into a single 4D model that incorporated geometries, volumes and schedules for all elements as well as the identifiers used in the original 3D models or 2D drawings.

All project participants had similar local models in their use – the management contractor Lemcon, structural designer Finnmap, steel supplier and frame constructor PPTH, and Tekla, the partner responsible for the pilot’s technical implementation. The models were kept identical through mutual synchronisation. Tekla Structures makes it possible to save a virtually unlimited volume of status data in a single model. But because construction work had already begun when the pilot got underway and the partners had been brought together at short notice, a decision was made to work with relatively simple yet essential assembly and manufacturing data.

Scheduling was carried out by management contractor Lemcon and steel supplier and frame constructor PPTH. Collaboratively they defined the assembly sequence and followed the assembly dates in the 4D model. The plan and its realisation were kept fully up to date in the model with daily updates to schedule changes and realised assembly dates. In the pilot, the partners received up-to-date situation reports in attribute format for entry into their own models. Assembly situation reports were produced from the 4D model beforehand or afterwards for a specific day or week, for example.

Schedules on track through simulation
According to Lemcon Project Manager Juha Höyhtyä, the 4D model validated itself during the pilot as a powerful tool for site management. Its ultimate capabilities were proven when the tightly scheduled project was threatened by a delay of several weeks in autumn 2004.

“A crisis emerged when a frame subcontractor fell behind schedule at a point where the frame assembly and interior work met. If we hadn’t taken action, both the interior work and fitting the heating, plumbing, air-conditioning and other building services would have been significantly delayed,” Höyhtyä said. A traditional line schedule assessment showed that the building schedule could be squeezed a little but not enough. “We used the building information model to test how things could be made to work. We entered the maximum amount of work for each day and examined the possibilities. When we assessed the situation in detail with the subcontractor, the impossible started to look more promising after all.”

The building information model was used to carefully plan and simulate the assembly sequence for the next three weeks. With the management of dimensions and masses among its capabilities, the model supports tasks like planning hoisting. An option to view the assemblies for each day in a different colour aided visualisation. “I was promised that the critical stage would be completed one Saturday in October at 3 pm. It was actually finalised a couple of hours earlier,” Höyhtyä said.

Benefits measurable in dollars
Höyhtyä described the product model as a functional tool that communicated the site’s real situation with great reliability. The model facilitated the monitoring of site activity and the management of volumes, for example, and solidified the commitment of the project’s various parties to the schedule. Communication was also enhanced.

“I believe that a good experience could bond the parties involved more permanently. In future it would be good to bring in the concrete element suppliers to utilise the product model more extensively than for schedule and logistics planning alone. With the steel structures, the pilot achieved a level where the drawings required for production were produced directly from the model,” Höyhtyä said.

He believes the most significant cost benefits will in the future be derived from better schedule management and fewer errors since the use of a building information model enhances cooperation between design, pre-fabrication and assembly. He emphasised that cooperation requires an open and honest operational culture from each party in the value chain. “This would make it possible to switch from partial optimisation to cooperation that strengthens the productivity of the entire value chain and ultimately benefits the customer,” Höyhtyä concluded.

Cookie Consent

We use cookies to personalize your experience. By continuing to visit this website you agree to our Terms & Conditions, Privacy Policy and Cookie Policy.

Kennametal
B2B eMagazine December 2024
B2B eMagazine December 2024

Events

Constro 2025
Weldtech 2025
Chhattisgarh Mining Show
Odisha Mining Show
Metal Forming Expo
Roof India

Our Partners

Avians Innovations Technology
Volvo Penta
MB Crusher
Bullflex Rubbers
Cloos India Welding Technology
JSW Cement
Filtrec
Tacklers
BKT
Volvo
Blastline India
Sec RJMT
Power Screen
OLI Vibrators India
RSB Transmissions
Roots Auto Products
Rossi Gearmotors India
Abhay Rana Infra Service
Supreme Industries
Vermeer India
Ashar Locker India
Baudouin India
Doosan
Indo Chain
bondioli
Aquarius Engineers
Esquire Machines
Siddhivinayak Engg
Hectronic
Forech
Burner India
Mallcom
Kamlesh Metal
Tripcon
Terra Form Geotech
XPS India
Locwel
Molygraph
Velvex
RDC
Kennametal
SNTP
NBC Bearings
Enovation
HYVA
MMD
INGECO
Vishwakarma Perforators
Swagath Urethane Pvt Ltd
Build Smart